Tavantolgoi Railway Co., Ltd. is continuing the construction of the Gashuunsukhait-Gantzmod port cross-border railway step by step according to the plan, fulfilling the role of customer control.
As part of the project, geodetic points were verified on July 06-08, 2025. Specifically, three-dimensional geodetic location and height fixed points, which are the basis of the construction work, have been prepared, and the general contractor, China Railway Construction Corporation (CRCC), has made measurements and verified whether they are suitable for use.
According to the construction schedule, as of July 15, 2025, the following works have been completed. It includes:
A total of 603 holes in the barrier fence located in the closed area were prepared and 16 fixed posts were drilled. Also, 27 hard points have been dug and prepared.
Currently, there are 27 Chinese employees working within the borders of Mongolia, including 6 engineers and technicians, 1 cook, 1 translator, and 19 assistants (earthworks).
However, a total of 45 Chinese employees are working in the Mongolia-China shared zone.
Also, from the Mongolian side, R. Otgonsuren, Head of Customer Control Department, Chief Engineer B. Tungalagmören, and Driver G. Otgonbayar of “Tavantolgoi Railway” LLC are currently working in the border area, and a 10-person engineering and technical team will also work from today.
Technically, it is operating with 2 foundation drills, 3 cranes, 1 bucket, 3 excavators, 1 mixer, 1 water machine, and a total of 12 equipment.